Minutes May 2004
C: SYSTEM PROTECTION SUBCOMMITTEE
Chair: D. Novosel
Vice Chair: T. Seegers
The System
Protection Subcommittee met on May 19th, 2004 at 4:30 PM in St Louis, Missouri.
47 people attended the meeting, including 18 members.
10 WGs met at this meeting.
The chairman asked for
literature on blackout related matters. This material will be to inform the
industry on PSRC activities and share the results. Marc Carpenter is
responsible for overall PSRC coordination.
WG Reports:
C1: Cyber
Security Issues for Relaying
The C1 working group met with
6 members and 12 guests. John Tengdin made a presentation of Cyber Security
Tools for SCADA and Substation Automation and the remaining time was spent on
defining the outline of the report.
The assignment was not
changed but the wording was slightly modified for clarity:
-
To prepare a report
documenting the status of cyber security standards and to recommend
procedures and guidelines for cyber security for protective relays
-
To provide a liaison to
other agencies preparing cyber standards in fields related to relaying
-
To provide timely review
from a relaying perspective of draft documents prepared by other agencies
Furthermore, we decided that
‘Cyber Security’ as considered by this group should encompass all ‘Electronic
Data’ as related to Relaying, i.e. both local and remote access should be
included.
We extended the report due
date from the previous May 2005 target to September 2005. This is still a very
ambitious schedule. Hopefully, assignments can be handed out at the next
meeting and a draft developed soon after.
The outline was discussed but
not finalized to an extent to hand out assignments. The sections to be included
are:
Even though no assignments
were handed out it was commented that SEL’s papers could provide information
about password handling, and possibly also other aspects.
Some issues about network
security (or lack thereof) were discussed and Joe Gould, RuggedCom, was invited
to make a ‘Networking Overview’ presentation at the next meeting.
Dennis Holstein requested an
Email Exploder on our behalf and the web site http://grouper.ieee.org/groups/psrc/ctf1/
and several folders exist. Dennis has volunteered to be the administrator for
these functions.
However, due to some problems
the members email addresses are not posted. As soon as this is corrected,
Dennis will send out an email to all members to let them know that the list
exploder is working correctly.
Meeting minutes and documents
produced or reviewed by the group will be posted on the website and the members
will be notified when they are posted or updated. Everything that needs to go
up on the website should be sent to Dennis Holstein (holsteindk@adelphia.net).
Cyber security tools for
SCADA and Substation Automation
John Tengdin presented a
‘Recommended Practice (AGA12) for the retrofit of serial SCADA links and the
access to IED dialup maintenance ports’ being developed by Gas Technology
Institute. The presentation will be posted on our web site.
OPUS Publishing is involved
in a development project for these security tools that involve both application
software and hardware at the IED end. Trial installations are underway and we
look forward to receive updates from John.
Cigré
CIGRE JWG D2/B3/C2 is
developing a series of papers on cyber-security. They had initially invited C1
to a meeting in June but the meeting was postponed until some later date.
Dennis Holstein will keep us informed about any requests from this CIGRE working
group.
C2: Power Quality Issues in Protective Relaying
C2 met Tuesday May 18, 2004
in St. Louis, MO with 6 members and 7 guests present. The total number of members is 26.
No additional comments or
writing sections have been turned in since the last meeting. TW Cease and Steve Kunsman will take the
report content, add the summary, conclusion and make editorials for the final
draft report. The report will be issued
for ballot by July. Comments and ballot
responses are to be received by the end of August and will be presented at the
next WG meeting in September. The
report will be concluded at that meeting.
Steve Kunsman will find an
IEC and EN expert in Europe to comment on section 3.4 & 3.5.
TW reviewed the open action
items from last meeting. Actions
complete from last meeting:
Section 3.6.1 Writing assignment on issues of PQ monitoring and relays - Steve Kunsman
Again - all members have been
asked to review the document. The
latest version of the document will be posted on the IEEE PSRC C Subcommittee
website under WG C2. The link to the
PSRC site will be provided in the distribution of the minutes along with the
document.
Old Issues:
Eric Gunther will identify
other IEEE PQ documents that can be used for inclusion or reference in the C2
document.
Eric Gunther proposed that
the C2 document be provided to the IEEE Standard Coordinating Committee 22 that
is the PQ coordinating body for all of the IEEE. They can review and provide comments to the C2 working group.
Action Items:
1. Section review assignments due June 24, 2004
Section 6 – Roger Hedding
All sections – all members
2. Additional writing assignments due June 24, 2004
Section 3.6.3 Application of ITI Curve for
Distribution Networks - Patrick Carroll
Summary/Recommendation paragraph on next steps to the paper - Eric Udren
3. Eric Gunther to distribute a recently published paper
on PQ in Word format. Sections maybe
used for inclusion in the paper.
4. Update and provide comments on bibliography - Sidhu
5. TW to send out a ballot document requesting PSRC
members for comments and approval.
C3: Processes, Issues, Trends, and Quality Control of Relay
Settings
Working Group C3 met Tuesday,
May 18, 2004 in St. Louis, MO in a single session with 8 (of 21) members and 15
guests participating. Five of these
guests requested to become new members increasing the total membership to 26.
There was some discussion
concerning the intended output of the working group (paper, report,
guide). The general consensus was that
the nature of the material being covered did not warrant a guide. It was subsequently decided that the output
of the working group, at least for now, will be a PSRC report, with an
associated Transactions paper summarizing the report. Target date for completion is 2006.
The balance of the session
was taken to review the draft outline and enlist more volunteers for the
different sections. The different
volunteers were noted on the latest draft outline, which will be e-mailed to
all members and interested guests. Discussion items of note include:
A first draft for each
section should be sent to the Chair/Vice-Chair by August 16, 2004, so that the
sections can be combined into a first overall draft of the report, which will
be reviewed at the September meeting.
Reminders will be sent in June and July to each section owner.
Next meeting request
single-session, 30 participants, with computer projector.
Action Items:
1)
Refine the Outline Section details and start working on the section
content. A first draft of the section
is due August 16, 2004 - Outline
section owners and assistants
2) Send any relevant
references to vice-chair for inclusion in Reference section – All members
3) Send any suggestions
for needed definitions to vice-chair for inclusion in Definitions section – All
members
C4: Industry
Experience with Remedial Action Schemes
WG C-4 held its first meeting for one sessions today
with total 19 in attendance. Ten (10)
attendees signed up to be WG members.
a)
Review of
Assignments
The attendees discussed a
list of topics including:
·
Types of schemes to be
included in the survey - Should the survey encompass (wide area, UF, UV, any
form of none-conventional, or should it focus on the complex schemes
·
Should UV load shedding
schemes with multi-station be included?
·
Focus the survey such
that responses are clear and provide the reader with useful information
NERC 2002 definition of SPS
and RAS schemes was posted for the attendees to review and discuss as a
starting point.
A proposal was made for the
WG members to check the Regional Councils web sites or definitions of SPS and /
or RAS to verify if there are differences than the NERC definition and to help
the WG with preparing a definition for the type of schemes the survey should
include.
WG
Chair is also coordinating with PSRC CIGRE liaison.
Recommend we continue to use
terminology consistent with industry practice and familiarity
C5: Deployment
and Use of Disturbance Recorders
The meeting was called to
order at 4:30 P.M. Tueday, May 18, 2004 with 8 members and 10 guests in
attendance. Jim Hackett of Mehta Tech joined the working group as a member.
Chairman Barry Jackson resigned as chairman due to time constraints of the job.
Bill Strang assumed the chair. Tony Napokowski will be the vice-chair. Tony was
unable to attend this meeting due to a conflict in working group schedules.
Outstanding assignments were
reviewed, Alex Apostolov indicated he will submit outline section 2 by e-mail
following this meeting. Additional writing assignments were made to complete
the open sections of the outline. These writing assignments are requested to be
e-mailed to the chairman by July 15. They will be added to the initial draft
and posted on the working group web site prior to the next meeting. The
chairman will also attempt to edit a draft prior to the next meeting for a
single voice.
Larry Smith reported that due
to interest in the time stamp response of various IEDs to a change of current
magnitude, he had conducted a preliminary test of a number of units by various
manufacturers and designs. The initial results showed interesting results.
Larry will analyze these results and submit a report to the working group
intended as an annex to the paper.
C6: Relay
Engineering in Power Engineering Curricula
Working group C-6 met with four members and five
guests. The meeting was conducted by Juan M Gers. Copies of the minutes of the
last meeting in Tampa, Florida were distributed. During the meeting the content
of a course on electrical protections at senior elective level or 1st
year graduate was discussed. The course will be made up by self-contained,
stand-alone modules.
It
was agreed to distribute by e-mail the content that was discussed, so that
members and guests can review it and present additions and/or modifications
prior to the next committee of C6 group when the course content should be
defined and the modules allocated among members for writing and development.
C7: Protection System Testing
WG C-7 Met on May 18 in two sessions with total 40 (20
M, 20 G) in attendance:
b)
Review of
Assignments
The WG members reviewed
several contributions and exchanged comments and observations and also had a
presentation by Mladen Kezunovic.
Writing assignment topics
discussed included:
·
Interlocking and Control
functions inherent to the protective schemes will be included in the writing
assignments for the purpose of system testing
·
Balance of security vs.
dependability (Out of step). Importance
of line testing
i.
Testing for various
types of faults, applying faults to different phases and inception angels,
closed loop tests (dynamic / non-linear tests).
ii.
One of the examples
discussed is about the recent newsworthy events that have captivated our
attention (August 14, 2003) and whether methods of system testing would be able
to identify some of the contributing elements in advance to be rectified.
·
Testing of combination
of devices as a system
·
Open-loop and closed
loop system testing solutions
·
Cost effective and
easy-to-use techniques
·
Flexibility for
adjusting / adopting to system changes
·
Each section to reflect
on the incremental differences of system testing in comparison to the
conventional test methods, and the advantages of new protection system testing.
·
Discussion on the scope
clarification to include Control functions associated with protection.
Suggested Updated Scope:
The Working Group will
develop a guide for Power System Protection Testing. The Guide will include System Application Test Requirements,
Scope and level of tests and benefits of system testing for overall protective
schemes. This assignment encompasses
overall system testing procedures (generators, line, transformer, reactors,
capacitors, SPSs, end-to-end testing, distributed application within
substation, etc.), data collection requirements, as well as the test procedure
definitions. The WG will describe the
methods, extent, and types of system tests for protection at various voltage
levels and applications. Interlocking and Control functions inherent to the
protective schemes will be included in the writing assignments
c)
One presentation by Mladen Kezunovic covering
New ways of using permanent
test installations, field units and lab set-ups to evaluate / trouble shoot
protective relay operations
C8: Phasor-Based Models for Analyzing Relay
Performance
The Working Group did not meet during the PSRC
meetings in St. Louis, MO.
The Vice Chair reported that editorial changes
suggested in Draft 9 were incorporated in Draft 10, which was submitted to the
members of the C Subcommittee for comments of substance. No such comments were received. The draft was then submitted to the Officers
of the PSRC for approval. The approval
was received. The paper will be now be
submitted for publication in the IEEE Transactions on Power Delivery.
Subcommittee
will keep the wg active pending discussion.
C9: Application of Protective Relays
used for Abnormal Load Shedding and Restoration
Met with 9 members and 11 guests
The
working group met on Wednesday, May 19th, with 9 members and 11 guests present. Draft 4 of the document had been circulated,
with an informal working group survey to solicit comments.
The
working group discussed the schedule for proceeding to ballot the document:
-
resolve internal
negative responses by May 19th (today)
-
submit revised document
(Draft 5) to IEEE Editor by June 18th
-
revise Draft 5, based on
Editor’s comments by July 15th
-
convert document to pdf
and upload to the IEEE Web Site by July 31st.
The remainder of the
session was used to review comments. The one negative response was resolved.
Additional comments will be sent to the review committee for review and
incorporation into Draft 5.
C10: Effects on Changing Utility Environment on
Protective Relaying
Working group C-10 met,
Tuesday, May 18, 2004 with 15 attendees.
Version 5 of the WG
Report was distributed to all members and interested guest.
Discussions centered
around editorial changes necessary to make the report more readable. Version 6 of the report will be submitted to
Sub-Committee C for final approval.
After acceptance from SC-C the recommendation of the Working Group is to
be dissolved.
C11: Protection Issues during System
Restoration
The
working group met on May 18, 2004 with 5 members and 6 guests in
attendance. The paper was balloted
successfully by the working group and sent to the subcommittee and officers for
comment/approval. At this meeting, the
comments received from Charlie Henville were discussed and resolved. Bill Kennedy and Alex Apostolov agreed to
give a final reading to the paper. The
paper will then be sent to IEEE for publication in the “Transactions on Power
Delivery.”
Power System Analysis, Computing & Economics Committee
Liaison by Malcolm Swanson
No activities to report
NERC by Phil Winston
NERC is initiating a zone 3
application review. We are the body to
respond as the experts on relaying. We
currently have 9 PSRC members on the review group.
Liaison Report of the IEEE PES Power System Stability
Controls SC to the PSRC
No activities to report
Old Business
C
Web site has been updated
New Business
Investigate
performance of protective systems on protected equipment during stressed
conditions including discussion of dependability vs security.
Formed
a task force with the title: TF12 Performance of Relaying during Stressed
Conditions
George
Bartok/Damir Novosel will chair the task force to meet in September.